report here Reposition
report here
Potholes
Reported via desktop in the Road Defect category anonymously at 21:33, Friday 17 February 2023
Sent to Bromley Council less than a minute later. FixMyStreet ref: 4242554.
2 potholes in this area of the road getting bigger and unavoidable to miss when driving as they are in the middle of the road
Updates
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council
at 21:34, Friday 17 February 2023
-
Appropriate action has been taken to resolve the issue.
State changed to: Fixed
Posted by Bromley Council
at 10:51, Monday 27 February 2023
-
Never really repaired properly like most of the numerous potholes in the Borough , these particular potholes have now returned ! Contractors doing repairs quickly with little care for attention!
State changed to: Open
Posted anonymously at 09:27, Saturday 18 March 2023
Still open, via questionnaire -
3 of the 4. Nearly came off my motorbike I’m the dark on the long one. So dangerous. Your roads are horrific even new road surfaces crumble in no time and you allow contralto cut them and patch them without proper repair . Shocking
Posted by Daniel Witt-Morris at 20:35, Tuesday 4 April 2023
-
These were never repaired all they did was spray a line around them which is now almost washed off they are outside 66 and 80 Oaklands
Posted anonymously at 07:54, Wednesday 5 April 2023
-
Our contractor has been notified to take the appropriate action.
State changed to: In progress
Posted by Bromley Council
at 12:39, Wednesday 5 April 2023
-
Definitely not fixed, tried to avoid them yesterday!
Further up towards Norheads Lane by the School road conditions awful...Likewise the entire road from St Winifreds Road A233 and Grays Road resembles an unmade road rather then an A road with cars avoiding crater like potholes dangerously, an accident waiting to happen hopefully with no fatalities, be warned!!
State changed to: Fixed
Posted anonymously at 10:10, Saturday 15 April 2023
-
Thank you for your further comments regarding this issue. Bromley are aware of the significant volume of works raised and outstanding with our contractor and we are continuing to monitor and liaise with them over this outstanding schedule of works. Our Officers are not able to give precise timeframes to individual jobs at this moment but are continuing to undertake regular safety inspections and check any reported issues. We will continue to work with our contractor to ensure that all outstanding jobs are addressed as quickly as they are able.
State changed to: In progress
Posted by Bromley Council
at 19:32, Sunday 16 April 2023
-
Further works are necessary to resolve the issue and have been scheduled for action.
Posted by Bromley Council
at 13:41, Tuesday
Provide an update
Your information will only be used in accordance with our privacy policy