A number of potholes on the approach to the right hand turn.

Reported via desktop in the Potholes / Highway Condition category anonymously at 11:08, Wed 18 January 2023 using FixMyStreet Pro

Sent to Northamptonshire Highways less than a minute later. FixMyStreet ref: 4144285.

A number of potholes on the approach to the right hand turn .

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 11:08, Wed 18 January 2023

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Regarding this section of Church Lane, we are pleased to confirm that the carriageway defects that meet the specifications for remedial work, have a repair scheduled to resolve them. This should be completed within six months’ time. Please be assured that you will receive an update once repairs are concluded. We usually find these defects are tended to within 13 weeks.

    Posted by Northamptonshire Highways at 13:05, Mon 23 January 2023

  • Several of the potholes are now within the council guideline for need fixing. The one of concern is the one at the centre of the road which is a real danger to motorcycle riders(Tram Track)

    Posted anonymously at 05:38, Mon 13 March 2023

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 11:03, Mon 26 June 2023

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 13:32, Wed 28 June 2023

  • Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)

    State changed to: Fixed

    Posted by Northamptonshire Highways at 13:59, Wed 28 June 2023

This report is now closed to updates from the public. You can make a new report in the same location.