Damage to asphalt part of the pavement outside 49 Greencourt Road Petts Wood
Reported via mobile in the Pavement Defect category anonymously at 08:21, Wednesday 11 January 2023 using FixMyStreet Pro
Sent to Bromley Council less than a minute later. FixMyStreet ref: 4112436.
Yesterday contractors employed by Bromley Council removed a stump of a former street tree outside 47 Greencourt Road. See photo 3. They parked their vehicle plus trailer outside 49 Greencourt Road. This morning, I noticed damaged to the asphalt edge of the pavement. This was in tact yesterday morning at 08:30.
There is a large hole where the surface of the tarmac has been damaged with large chunks of asphalt over the pavement. See photos 1 & 2. I do not know if the contractors stump removing equipment was responsible for this damage.
This is now a trip hazard for pedestrians. Please can this be repaired as a matter of urgency.
Many thanks
Updates
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council
at 08:21, Wednesday 11 January 2023
-
Our contractor has been notified to take the appropriate action.
Posted by Bromley Council
at 12:49, Wednesday 11 January 2023
-
This matter is still outstanding. Please can you give an indication of when the section will be retarmaced. Thank you
Posted anonymously at 10:06, Monday 30 January 2023
-
Thank you for your update, Works raised at time of inspection remain outstanding with our contractor and is awaiting completion.
Posted by Bromley Council
at 11:55, Wednesday 1 February 2023
-
Appropriate action has been taken to resolve the issue.
State changed to: Fixed
Posted by Bromley Council
at 13:55, Wednesday 8 February 2023
-
Our contractor has been notified to take the appropriate action.
State changed to: In progress
Posted by Bromley Council
at 05:40, Friday 17 February 2023
-
The asphalt has been repaired but in the process of doing so your contractor damaged a paving slab which is cracked in three places. This needs to be inspected as this repair has not been carried out in a totally satisfactory manner.
Posted anonymously at 06:50, Friday 17 February 2023
-
This has been passed to our contractors to rectify
Posted by Bromley Council
at 18:07, Monday 6 March 2023
-
Thank you for your update, Further works raised with our contractor remain outstanding and is awaiting completion. We apologise for the delay.
Posted by Bromley Council
at 13:00, Tuesday 18 April 2023
-
Thank you for your further comments regarding this issue. Bromley are aware of the significant volume of works raised and outstanding with our contractor and we are continuing to monitor and liaise with them over this outstanding schedule of works. Our Officers are not able to give precise timeframes to individual jobs at this moment but are continuing to undertake regular safety inspections and check any reported issues. We will continue to work with our contractor to ensure that all outstanding jobs are addressed as quickly as they are able.
Posted by Bromley Council
at 13:24, Thursday 11 May 2023
Provide an update