Multiple Pot holes

Reported via desktop in the Potholes / Highway Condition category anonymously at 19:50, Wed 21 December 2022 using FixMyStreet Pro

Sent to Northamptonshire Highways less than a minute later. FixMyStreet ref: 4051054.

Pot hole on the left hand side of the road slowly becoming bigger and developing others

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 19:51, Wed 21 December 2022

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Regarding this section of Harrowden Road, we are pleased to confirm that the carriageway defects that meet the specifications for remedial work, have a repair scheduled to resolve them. This should be completed within six months’ time. Please be assured that you will receive an update once repairs are concluded. We usually find these defects are tended to within 13 weeks.

    Posted by Northamptonshire Highways at 12:23, Thu 29 December 2022

  • Pot holes getting worse! And spreading up the road and to the centre, needs attention...

    Posted anonymously at 19:26, Sun 2 April 2023

  • Why has only half of the pot holes been completed ??

    Posted anonymously at 23:39, Mon 5 June 2023

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 11:02, Wed 14 June 2023

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 07:42, Thu 15 June 2023

  • Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)

    State changed to: Fixed

    Posted by Northamptonshire Highways at 08:37, Thu 15 June 2023

This report is now closed to updates from the public. You can make a new report in the same location.