Large pothole

Reported via desktop in the Road Defect category anonymously at 09:19, Tue 8 November 2022 using FixMyStreet Pro

Sent to Bromley Council less than a minute later. FixMyStreet ref: 3947212.

This has been there for a few weeks and is liable to cause damage to cars

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 09:20, Tue 8 November 2022

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 12:00, Tue 8 November 2022

  • Large pothole forming on Blackrook Lane in left hand lane as you approach roundabout with Bickley Park Road, it's towards the right hand side of the lane and you hit it when you go to move across the flat roundabout.

    Posted anonymously at 07:16, Wed 14 December 2022

  • This is still there and getting worst !

    Posted anonymously at 15:00, Wednesday 4 January 2023

  • As outlined at: http://www.bromley.gov.uk/ fixservices please allow up to 35 days for remedial works to be undertaken.

    Posted by Bromley Council at 10:28, Friday 6 January 2023

  • Appropriate action has been taken to resolve the issue.

    State changed to: Fixed

    Posted by Bromley Council at 10:49, Friday 6 January 2023

  • Our contractor has been notified to take the appropriate action.

    State changed to: In progress

    Posted by Bromley Council at 10:52, Friday 6 January 2023

  • Pot hole still getting bigger!! this was reported some time ago and still nothing

    Posted anonymously at 16:28, Friday 13 January 2023

  • Please bear with us. these works are still outstanding with our Minor Works contractor and will be completed soon.

    Posted by Bromley Council at 11:13, Friday 20 January 2023

  • Appropriate action has been taken to resolve the issue.

    State changed to: Fixed

    Posted by Bromley Council at 14:43, Thursday 26 January 2023

  • Our contractor has been notified to take the appropriate action.

    State changed to: In progress

    Posted by Bromley Council at 12:15, Sunday 26 March 2023

  • We are sorry that this work has not yet been completed. We are working with our Minor Works contractor in an effort to resolve this issue.

    Posted by Bromley Council at 09:08, Wednesday 26 April 2023

  • Appropriate action has been taken to resolve the issue.

    State changed to: Fixed

    Posted by Bromley Council at 13:58, Friday 12 May 2023