Resurfacing not finished oroperly
Reported via mobile in the Road Defect category anonymously at 16:43, Sat 29 October 2022 using FixMyStreet Pro
Sent to Bromley Council less than a minute later. FixMyStreet ref: 3923541.
Oakwood Gardens was resurfaced last Thursday. The tarmac was not fully removed before resurfacing out side Mayfield. The new tarmac is not finished correctly to the kerb as a result, is standing proud and already crumbling
Updates
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council
at 16:43, Sat 29 October 2022
-
Further works are necessary to resolve the issue and have been scheduled for action.
Posted by Bromley Council
at 09:08, Mon 7 November 2022
-
No work has been undertaken to fix the issue
Posted anonymously at 12:29, Thu 8 December 2022
-
We can confirm we are still awaiting a programme date from our contractor that these remedial works. Once this has been programmed we will provide a further update.
Posted by Bromley Council
at 13:41, Monday 30 January 2023
-
Any idea of time scales please?
Posted anonymously at 13:14, Friday 17 March 2023
-
We are sorry for the lack of update regarding this issue. After another joint inspection with the contractor about theses works a method of working has been agreed, due to the levels available works will have to be carried out to the crossover as well as the carriageway. The council will send a letter out shortly to the homeowner to provide further information on the remedial works.
Posted by Bromley Council
at 10:00, Monday 27 March 2023
-
We have investigated this report and have made contact with the report originator to outline further details. This report is now closed on FixMyStreet.
State changed to: No further action
Posted by Bromley Council
at 15:48, Thursday 13 April 2023
-
Resident of Mayfield on Oakwood Gardens has called back as the concrete has been dug out on Monday, blocks have been delivered but no crew have returned, they are unable to access the drive at the moment and need to m over a car this weekend.
State changed to: Open
Posted anonymously at 10:06, Thursday 18 May 2023
-
Whilst the pavement and kerb has been sorted, the tarmac was cut back by the workmen and there remains a gap between the tarmac and the kerb. Can you please get the contractor to come back and fix this.
Posted anonymously at 08:03, Wednesday 24 May 2023
-
This has been ongoing now for 208 days
Posted anonymously at 20:08, Wednesday 24 May 2023
Provide an update