Reported via desktop in the Road Defect category anonymously at 12:53, Sat 29 October 2022
Sent to Bromley Council less than a minute later. FixMyStreet ref: 3923075.
Been waiting for over a month for fix to large pothole on Bromley side of roundabout. You could bury a Fiat 500 in it. V dangerous esp to 2 wheelers in dark or wet, please fix without further delay!
Updates
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council
at 12:54, Sat 29 October 2022
-
Our contractor has been notified to take the appropriate action.
Posted by Bromley Council
at 11:01, Mon 31 October 2022
-
Eventually fixed after weeks of chasing. Poor quality original repair on area where problems regularly occur. See how long the fix lasts this time. Not holding my breath, didn't look too good on Thursday last!
State changed to: Fixed
Posted anonymously at 10:30, Sun 27 November 2022
-
Appropriate action has been taken to resolve the issue.
Posted by Bromley Council
at 11:37, Thu 1 December 2022
-
Appropriate action was ineffectual. Hole needs filling PROPERLY again! Any chance of a proper fix preferably before XMas (2020)! Report recorded 11.40 today, Thursday.
Posted anonymously at 12:13, Thu 1 December 2022
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council
at 06:40, Thu 29 December 2022
-
We are continuing to investigate and working to resolve this report
Posted by Bromley Council
at 06:46, Thu 29 December 2022
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
Posted by Bromley Council
at 07:05, Thu 29 December 2022
-
Our contractor has been notified to take the appropriate action.
Posted by Bromley Council
at 10:31, Thu 29 December 2022
-
Please bear with us. These works are still with our Minor Works contractor and will be completed soon.
Posted by Bromley Council
at 14:39, Thursday 26 January 2023
-
Appropriate action has been taken to resolve the issue.
State changed to: Fixed
Posted by Bromley Council
at 11:31, Friday 17 February 2023
-
Our contractor has been notified to take the appropriate action.
State changed to: In progress
Posted by Bromley Council
at 07:03, Tuesday 21 February 2023
-
Bromley are aware of the significant volume of works raised and outstanding with our contractor and we are continuing to monitor and liaise with them over this outstanding schedule of works. Our Officers are not able to give precise timeframes to individual jobs at this moment but are continuing to undertake regular safety inspections and check any reported issues. We will continue to work with our contractor to ensure that all outstanding jobs are addressed as quickly as they are able.
Posted by Bromley Council
at 14:06, Tuesday 4 April 2023
-
Now lets see, reported 6 months ago, and many times thereafter,and still outstanding. Time to find fresh contractors perhaps, or is it only taxpayers money/value, so it doesn't really matter. Are you also aware, and just ignoring the generally dangerous state of this road all the way through to Westerham Hill? I thing there are better roads in the Ukraine warzone, which you may think is funny, but I think you should all hang your heads in shame. What do we pay our (recently increased) council taxes for again?
Posted anonymously at 15:09, Tuesday 4 April 2023
-
The issue has been re-attended and additional works completed. If the issue re-occurs please re-report via: https://fix.bromley.gov.uk
State changed to: Fixed
Posted by Bromley Council
at 14:04, Tuesday 11 April 2023
This report is now closed to updates. You can make a new report in the same location.