Fixed
Tree damaged by school Delivery and need pruning
Reported via mobile in the Tree Requires Pruning category anonymously at 12:24, Mon 10 October 2022 using FixMyStreet Pro
Sent to Bromley Council less than a minute later
Large amount of extremely high growing trees at end of the meadow require pruning and inspecting as possible danger to school children walking through. Damage to tree following delivery to school.
Updates
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council
at 12:25, Mon 10 October 2022
-
Bromley Council are not responsible for maintaining private trees. Further information on your rights and options for dealing with overhanging trees from neighbouring private land can be found at the Citizen's Advice website: http://www.adviceguide.org.uk
State changed to: third party responsibility
Posted by Bromley Council
at 16:00, Tue 11 October 2022
-
These trees are not on private land. The meadow is a highway as previously pointed out by your representative who left a note concerning traffic cones.
Posted anonymously at 22:11, Tue 11 October 2022
-
Thank you for your comments. LBB does not own any of the trees along Mead Road with private TPO's on a number of the trees. We will investigate this further.
State changed to: In progress
Posted by Bromley Council
at 11:08, Tue 18 October 2022
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
Posted by Bromley Council
at 11:10, Tue 18 October 2022
-
Our contractor has been notified to take the appropriate action.
Posted by Bromley Council
at 09:55, Thu 20 October 2022
-
Thank you for your patience whilst we work to resolve your enquiry.
Posted by Bromley Council
at 13:55, Fri 2 December 2022
-
The contractor has been instructed to undertake works as a priority, thank you for your continued patience.
Posted by Bromley Council
at 08:31, Monday 16 January 2023
-
Further works are necessary to resolve the issue and have been scheduled for action.
Posted by Bromley Council
at 08:07, Friday 27 January 2023
-
Our contractor has been notified to take the appropriate action.
Posted by Bromley Council
at 08:10, Friday 27 January 2023
-
Appropriate action has been taken to resolve the issue.
State changed to: Fixed
Posted by Bromley Council
at 07:31, Wednesday 1 February 2023
Provide an update
Your information will only be used in accordance with our privacy policy