report here Reposition
report here
Lamppost damaged
Reported via desktop in the Lamp Column Damaged category by Bromley Council at 23:14, Fri 7 October 2022 using FixMyStreet Pro
Sent to Bromley Council less than a minute later. FixMyStreet ref: 3875848.
Call from metropolitan police: RTC - car hit lamppost Beckenham High Street junction of Manor Road with wires exposed. Possibly another damaged post. Incident number 8114 07/04/2022.
Updates
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council
at 23:14, Fri 7 October 2022
-
J B Riney have attended. Lamppost is bent but solid in ground and will not fall. Will need to be replaced in next few weeks. Traffic lights are out for junction as car has flattened one set and is currently still in situ on them. Contractor on scene dealing and warnings have been put out. Awaiting car recovery.
State changed to: Fixed
Posted by Bromley Council
at 00:17, Sat 8 October 2022
-
Member of public advises car has now been towed but debris is still in road and on pavement
Posted by Bromley Council
at 17:15, Sat 8 October 2022
-
JB Riney are attending to deal with the debris but will report back about any other issues when they arrive on scene
Posted by Bromley Council
at 17:20, Sat 8 October 2022
-
Further works are necessary to resolve the issue and have been scheduled for action.
State changed to: In progress
Posted by Bromley Council
at 13:28, Mon 10 October 2022
-
We have programmed the works for week commencing 7th November 2022, if we are unable to resolve the issue on this visit, we will reprogram the works. Thank you for your patience.
Posted by Bromley Council
at 11:26, Fri 28 October 2022
-
We are experiencing extremely long lead times and waiting for materials to resolve this job. Thank you for your patience.
Posted by Bromley Council
at 09:34, Tue 6 December 2022
-
We are currently waiting for delivery of materials to enable us to fix the problem. These are expected to be delivered week commencing 16 January 2023. Thank you for your patience.
Posted by Bromley Council
at 13:38, Thursday 12 January 2023
-
We have a revised delivery date April 2023 to resolve the issue. Thank you for your patience.
Posted by Bromley Council
at 07:24, Thursday 16 February 2023
-
Apologies for the delay, we have another new delivery date May 2023 to resolve the problem.
Posted by Bromley Council
at 08:34, Thursday 30 March 2023
-
Any updates on this street light fix?
Posted anonymously at 22:48, Sunday 7 May 2023
-
We have programmed the works to start for week commencing 22 May 2023. Thank you for your patience.
Posted by Bromley Council
at 11:10, Tuesday 23 May 2023
Provide an update
Your information will only be used in accordance with our privacy policy