Flooding at the bottom of the kerb to cross The Avenue
Reported via mobile in the Pavement Defect category anonymously at 13:18, Wed 14 September 2022 using FixMyStreet Pro
Sent to Bromley Council less than a minute later. FixMyStreet ref: 3824835.
There is often flooding with the smallest rain near the kerb to cross from one end of 'The Avenue ' to the other. This is where 'The Avenue' intersects with Sevenoaks Road.
Updates
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council
at 13:18, Wed 14 September 2022
-
We have investigated this report and believe no further action is required at this time. The issue may be below our investigatory levels or may no longer be present. If this problem persists, please provide further comments to the report.
State changed to: No further action
Posted by Bromley Council
at 13:36, Wed 14 September 2022
-
Water stagnates around the kerb at the intersection between The Avenue and Sevenoaks Road. This is a result of faulty levelling at the time of the re-lay of the road last year and water does not pass through to the closest drainage as it used to happen before. Kindly please look into this faulty design.
Posted anonymously at 14:23, Wed 14 September 2022
-
No action required enquire closed
State changed to: Fixed
Posted by Bromley Council
at 13:13, Fri 23 September 2022
-
This is not resolved and there is a problem with the levelling to the drainage close to the kerb.
Posted anonymously at 14:55, Fri 23 September 2022
-
We are reinvestigating this issue and will provide an update in due course. Thank you for your patience.
State changed to: Investigating
Posted by Bromley Council
at 10:44, Mon 3 October 2022
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council
at 10:03, Wed 23 November 2022
-
Our investigations are ongoing, we appreciate your patience.
Posted by Bromley Council
at 15:00, Tue 6 December 2022
-
We are continuing to investigate and working to resolve this report
Posted by Bromley Council
at 15:04, Tue 6 December 2022
-
We apologise for the lack of update to this enquiry we have been waiting for a programme date from our contractor when the remedial works will be carried out. Works had been programmed before the Christmas break but due to the change in weather this was postponed, we hope to complete these works shortly.
Posted by Bromley Council
at 10:04, Monday 23 January 2023
-
Further works are necessary to resolve the issue and have been scheduled for action.
Posted by Bromley Council
at 08:59, Monday 20 February 2023
-
A defect on the Surface Water drainage assets at this location has been verified and remedial works are now on our works schedule.
State changed to: No further action
Posted by Bromley Council
at 09:54, Monday 17 April 2023