The pool has been shut for refurbishment long past the estimated timescale for the repair. The original date for completion of the works was Sept/Oct 2021. Pool staff refuse to give a date for reopening and the contractor states that they are having problems with the pool liner, despite the fact that both pools have been full of water for over two months now. I visit the pool to check on progress 2-3 times a week and I have only ever once seen anyone working on the pool in 4 months.
Updates
-
Still not opened and still no date for re opening despite the Everyone Active website stating that a date would be published by the end of January.
Posted anonymously at 10:25, Thursday 3 February 2022
Still open, via questionnaire -
Date now showing as April on website, time will tell. Supposed to be completed in Autumn 20121
Posted anonymously at 16:55, Thursday 3 March 2022
Still open, via questionnaire -
Still not open. Supposed to be opening again this month.
Posted anonymously at 14:51, Friday 1 April 2022
Still open, via questionnaire -
Just found out that the opening date has been put back another three weeks!
Posted anonymously at 14:15, Sunday 1 May 2022
Still open, via questionnaire -
Finally opened nearly a year late. Work completed looks like it could have been done in a couple of weeks.
State changed to: Fixed
Posted anonymously at 09:40, Monday 30 May 2022
Provide an update