Back to all reports

Large pothole on the verge leading to the rear of scotsgrove cottages

Reported via desktop in the Pothole category by Joanna Bonnett at 20:10, Tuesday 1 June 2021

Received by Buckinghamshire Council moments later

There is a large deep pothole on the verge/laneway leading from the A418 at scotsgrove onto to the track between scotsgrove cottages and 7 scotsgrove. This lane is a council lane and the fact the pothole has developed is causing considerable danger and damage to residents pulling off the A418 onto the council lane running between and around the back of 7 scotsgrove and scotsgrove cottages. The condition of the lane is heavily degraded starting with the above mentioned pothole which is the start of numerous potholes along the lane which are causing physical injury to the backs and necks of the elderly residents of scotsgrove cottages and needs to be repaired urgently.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 20:11, Tuesday 1 June 2021

  • Thank you for your report.
    We have completed our inspection of the defect, which we aim to repair within five working days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 09:27, Friday 4 June 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 09:27, Friday 4 June 2021

  • Thank you for your report.
    We have completed our inspection of the defect, which we aim to repair within five working days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 09:31, Friday 4 June 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 11:21, Friday 4 June 2021

  • Thank you for your report; we are pleased to advise that the repair of this defect is now in progress. We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 10:09, Tuesday 8 June 2021

  • We are pleased to tell you that the repair of this defect is now complete.

    Please consider completing our short survey below on how you found the repair;
    https://forms.gle/ FywWv2ZGrGb9XgCu8

    The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway.

    Regards
    Transport for Buckinghamshire

    State changed to: Fixed

    Posted by Buckinghamshire Council at 10:23, Tuesday 8 June 2021

This report is now closed to updates. You can make a new report in the same location.