Large pothole forming

Reported via iOS in the Pothole category anonymously at 10:16, Mon 2 December 2019

Received by Buckinghamshire County Council moments later

A pothole has appeared outside Long Colts Barn. The photo attached shows this. The person has a size 3 boot on. It is a busy little road.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire County Council at 10:20, Mon 2 December 2019

  • Thank you for your report.
    An initial assessment has been made and further work to investigate your enquiry is required. This should be completed within the next 10 days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire County Council at 11:57, Mon 16 December 2019

  • Thank you for your report.
    We have completed our inspection of the defect, which we aim to repair within five working days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire County Council at 10:41, Fri 20 December 2019

  • State changed to: In progress

    Updated by Buckinghamshire County Council at 10:41, Fri 20 December 2019

  • Thank you for your report.
    We have completed our inspection of the defect, which we aim to repair within five working days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire County Council at 10:41, Fri 20 December 2019

  • State changed to: In progress

    Updated by Buckinghamshire County Council at 14:29, Fri 20 December 2019

  • Thank you for your report, the repair of this defect is now in progress.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire County Council at 10:26, Tue 24 December 2019

  • We are pleased to tell you that the repair of this defect is now complete.

    The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway

    Regards
    Transport for Buckinghamshire

    State changed to: Fixed

    Posted by Buckinghamshire County Council at 10:30, Tue 24 December 2019

  • Still not fixed!

    State changed to: Open

    Posted anonymously at 11:04, Monday 6 January 2020
    Still open, via questionnaire