Replacement of block paving with 'cold roll' tar

Reported in the Road and Pavement Issues category anonymously at 21:10, Thu 7 November 2019 using FixMyStreet Pro

Sent to Bromley Council less than a minute later

Shortly after the very expensive completion of the remodelling of pavements in Beckenham High Street SGN carried out some work outside 63 High Street Beckenham. Rather than replacing the block paving that the workers removed, these were left stacked and the holes repaired with cold roll tar. The blocks were removed from the site a number of weeks later.Surely utility services should replace like with like particularly after such a comprehensive project on the High Street. The result is unsightly and doesn't reflect well on the improvements.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 21:10, Thu 7 November 2019

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 12:18, Tuesday 7 January 2020

  • Thank you for attending to the issue I raised, I noticed that the block paving had been replaced when I walked past the area last week.

    State changed to: Fixed

    Posted anonymously at 21:28, Saturday 8 February 2020

  • Thank you for your report the block paving as be completed we will do the resin when the weather improve

    Posted anonymously at 12:14, Thursday 13 February 2020

  • Our contractor has been notified to take the appropriate action.

    State changed to: In progress

    Posted by Bromley Council at 12:29, Tuesday 18 February 2020

  • Apologies for the delay in rectifying this issue, we are waiting for an improvement in the weather to enable the resin reinstatement to be carried out.

    Posted anonymously at 09:51, Wednesday 4 March 2020

  • To confirm the blocks in the footway have been replaced. Unfortunately due to COVID19 planned works in Bromley have been put on hold for the time being, when work is able to start again the council will replace the resin around the tree and carry out the carriageway repairs.

    Posted anonymously at 14:24, Monday 6 April 2020

  • The issue has been re-attended and additional works completed. If the issue re-occurs please re-report via: https://fix.bromley.gov.uk

    State changed to: Fixed

    Posted by Bromley Council at 11:22, Wednesday 15 July 2020

Provide an update

Your information will only be used in accordance with our privacy policy

Next: Tell us about you

or No personal details will be stored, and you will not receive updates about this report.

Your update

Tell us about you

Do you have a FixMyStreet password?