Block paving not reinstated after excavation work by utility company

Reported in the Road and Pavement Issues category anonymously at 12:49, Friday 11 October 2019 using FixMyStreet Pro

Sent to Bromley Council 1 minute later

At the junction of High Street Bromley and Harmony Way adjacent to the Picture House and The Star & Garter a utility company (Electric) has tarmaced the pavement instead reinstating the block paving. Also in Harmony Way there are two large steel plates where the carriageway has been dug up.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 12:50, Friday 11 October 2019

  • We are continuing to investigate and working to resolve this report

    Posted by Bromley Council at 14:38, Tuesday 15 October 2019

  • Thank you for your enquiry.

    We are already aware of this issue. These are specialist blocks and UK Power Networks are currently awaiting for blocks to be delivered so they can complete these reinstatement.

    Posted anonymously at 15:52, Monday 21 October 2019

  • We have investigated this report and found the issue to be the responsibility of UK Power Networks. We have therefore referred the enquiry to UK Power Networks.

    State changed to: third party responsibility

    Posted by Bromley Council at 15:53, Monday 21 October 2019