Back to all reports

Two month delay in repairing footway

Reported in the Road and Pavement Issues category anonymously at 15:10, Wednesday 13 March 2019 using FixMyStreet Pro

Sent to Bromley Council 5 minutes later

Footpath from Roseberry Gardens leading to Tubbenden Lane.

Issue number 1426602, patching which was marked up for repair by the Street Inspector, has still not been fixed (this was first reported on 8 January 2019, two months ago).

This footpath is used by a partially sighted person.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 15:52, Wednesday 13 March 2019

  • We are continuing to investigate and working to resolve this report

    Posted by Bromley Council at 17:15, Thursday 21 March 2019

  • Further works are necessary to resolve the issue and have been scheduled for action.

    Posted by Bromley Council at 13:51, Monday 1 April 2019

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 18:07, Friday 5 April 2019

  • Appropriate action has been taken to resolve the issue.

    State changed to: Fixed

    Posted by Bromley Council at 09:21, Sunday 19 May 2019

Provide an update

Your information will only be used in accordance with our privacy policy

Next: Tell us about you

Your update

Tell us about you

Do you have a FixMyStreet password?