Back to all reports

Subsiding crossing

Reported via Android in the Road and Pavement Issues category anonymously at 09:44, Saturday 16 February 2019

Sent to Bromley Council 1 minute later

Road is starting to subside at the crossing between the Partridge and what used to be the bell

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 09:48, Saturday 16 February 2019

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 13:19, Tuesday 19 February 2019

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 14:16, Wednesday 20 February 2019

  • For information, the order for this repair remains outstanding within our contractor's planned schedule of work. Further arrangements are currently being undertaken to provide traffic management and/or the necessary specialist equipment in order to undertake the works.

    Posted by Bromley Council at 13:25, Friday 8 March 2019

Provide an update

Your information will only be used in accordance with our privacy policy

Next: Tell us about you

Your update

Tell us about you

Do you have a FixMyStreet password?